Protect30A · Stormwater accountability
Walton County Stormwater: What the Records Show
Permit coverage, reporting and field work—each finding linked to evidence.
1 · The short answer
Walton County stormwater records are listed in DEP’s index, but current permit coverage, filing timeliness and compliance remain unverified in this review. DEP’s application tracker records receipt of FLR04E084-005-MS2A on April 20, 2023 and lists agency action as pending in data current November 4, 2026. See the application record. Protect30A’s November 4 review recorded 56 index entries across two pages, including two annual-report entries dated April 13, 2026. Individual file contents were not retrieved or examined. An index entry establishes a listing; it does not establish a complete filing, receipt date, approval or compliance.
DEP supplied the portal November 3 in case 00251779, facility reference FLR04E084. An accessible-copy follow-up was sent November 4. Walton County acknowledged request 26-915; targeted mailbox searches through November 4, 2026, 3:34 p.m. Central found no newer substantive county response. County request details remain uninspected: the NextRequest page requires sign-in, as checked November 4, 4:17 p.m. Central. Read the dated evidence register.
Evidence rule: An unanswered request, unavailable file or absence from an index is not proof of nonfiling or a violation. Agency statements and index titles are identified separately from findings supported by examined documents.
2 · What MS4 means—and why it matters
MS4 means Municipal Separate Storm Sewer System. The questions here concern the county’s stormwater permit program: whether coverage is current, whether required reports were received on time, and what inspection and maintenance records demonstrate. These are separate questions; one does not answer the others. County and DEP sources provide the program context.
3 · What the records confirm
| Question | Supported finding | Source and cutoff | What remains unverified |
|---|---|---|---|
| Current permit coverage | DEP identified facility FLR04E084 and supplied its records portal. | DEP response and index review; Nov. 4, 7:54 a.m. Central. | Current coverage dates, renewal disposition and DEP’s continuation instruction. |
| Renewal application | DEP’s application tracker records receipt of FLR04E084-005-MS2A on April 20, 2023 and lists agency action as pending in data current November 4, 2026. | DEP application events, reviewed November 5. | Application completeness, final disposition, current coverage and written Cycle 4 guidance. |
| Annual reporting | The inspected index lists YEAR 8 ANNUAL REPORT and WALTONCO_084_C5Y2_AR, both with Document Date April 13, 2026. | Index metadata and catalog identifiers; Nov. 4, 7:54 a.m. Central. | File contents, reporting periods, applicable deadlines, actual receipt dates and completeness. Document Date is not verified submission date. |
| County records request | County acknowledged request 26-915 on November 2. | Receipt documentation; targeted mailbox searches through Nov. 4, 3:34 p.m. Central. | No newer substantive response found in searched mailboxes. NextRequest page checked November 4, 4:17 p.m. Central; request details require sign-in and remain uninspected. |
| Inspection and maintenance | The county’s posted report lists 116 ponds maintained and approximately 1,048 roadway miles where ditch/swale maintenance are performed; supporting logs remain unverified. | County report, PDF page 13, BMP 6a 06; report period Oct. 15, 2023–Oct. 14, 2024. | Dated site-level completion, backlog, responsible owners and correction dates. Reported totals are not a work-log audit. |
4 · Timeline of filings and agency responses
Document dates, message receipt times and review dates have different meanings.
- April 20, 2023 — application receipt: DEP’s application tracker lists receipt of FLR04E084-005-MS2A.
- April 13, 2026 — index Document Date: Two report entries are listed. Receipt dates and reporting periods remain unverified.
- November 2 — requests and acknowledgments: County request 26-915 and DEP case 00251779 were acknowledged. Receipt alone establishes no compliance finding.
- November 3, 5:06 p.m. Central — DEP response received: Tommy Moore supplied the facility records portal.
- November 4, 7:54 a.m. Central — index review recorded: 56 entries across two pages; underlying file contents not examined.
- November 4 — follow-up sent: Accessible copies, receipt evidence and clarification of coverage and the two April report entries requested. No chargeable work authorized.
- November 4, 8:20 a.m. Central — DEP status message: Northwest District working on remainder; no records attached. Status and provenance.
5 · Questions still awaiting answers
Requests sent November 2; DEP document-access follow-up sent November 4. These are open questions, not findings of a violation.
- DEP: What coverage dates and renewal disposition are supported by agency records? What written instruction governed continuation of Cycle 4?
- DEP and county: Which periods do the two April 2026 entries cover, what deadlines applied, and when did DEP actually receive each required submission?
- DEP: What audit findings, corrective actions and closure records exist, and is responsive correspondence outside the public index?
- County: What inspection and maintenance records support reported work, and what unresolved items have an owner and completion date?
- County and district: What records establish ditch responsibilities, mosquito-control referrals and closure?
Full county request · Full DEP request. Requested management checkpoints and agency estimates are not statutory production deadlines.
Examined county report: what it reports, and what it does not prove
The county’s 2023–2024 annual report, PDF page 13, BMP 6a 06, reports 116 stormwater ponds maintained and approximately 1,048 miles of roadways where ditch and swale maintenance are performed. These are county-reported program totals for the report period October 15, 2023–October 14, 2024—not independently verified work orders or proof that every location was serviced.
Next evidence needed: Dated, location-specific maintenance logs and work orders, inspection results and closure records. Public posting of this report does not establish DEP receipt, timeliness, current permit coverage or a compliance determination. Review recorded November 4, 2026, 3:35 PM Central.
Public records request tracker
Two coordinated requests were sent and acknowledged on November 2. Florida DEP and FDEP are the same agency. Both November 2 acknowledgments are preserved. DEP supplied its records portal November 3; 56 index entries were inspected November 4. Underlying document access and review remain open. Acknowledgment establishes receipt only; it does not establish permit coverage, compliance, required reporting history, or completion of maintenance obligations.
| Custodian | Request | Status |
|---|---|---|
| Walton County | Coverage, submissions, field work and referrals | Acknowledged Nov. 2, 4:15 p.m. Central; 26-915. Receipt documentation · NextRequest (may require sign-in). No newer substantive county response found in targeted mailbox searches through November 4, 2026, 3:34 p.m. Central; NextRequest portal contents not independently inspected. |
| Florida DEP | Coverage determination, renewal, receipts and compliance file | Acknowledged Nov. 2, 4:08 p.m. Central; reference 00251779. November 3 portal response received; November 4 index review and accessible-copy follow-up completed. November 2 receipt · Evidence and access limits. November 4, 8:20 a.m. Central status reply: Northwest District working on the remainder; no record attachments. Underlying DEP documents not yet examined. |
DEP’s response supplied an index, now inspected; this is a substantive response beyond acknowledgment, but underlying document production and examination remain unverified. County correspondence was rechecked through November 4, 2026, 3:34 p.m. Central; no newer substantive response was located in searched mailboxes. Portal contents were not independently inspected. No independent compliance determination has been established. Unavailable records are not evidence of a violation. Structured request register. NextRequest estimates completion within 10 days, with a possible delay for the November 11 office closure; this is an agency estimate, not a statutory deadline. Fees require prior written approval. A status update was requested within 10 business days; this is not a statutory production deadline.
The evidence register records weekday reply checks and publication as active as of November 4, 2026. This page is a dated publication, not a live status feed. Reviews are periodic; the latest correspondence check was November 5, 2026. No new reply or release notice was located in the designated mailbox. County portal details remain access-limited; DEP’s tested annual-report View link still did not yield a readable document.
What remains to be answered
- Current coverage dates, permit identifier and renewal disposition.
- DEP’s actual instruction or basis for continuing Cycle 4 after October 14, 2023.
- Required reports, deadlines, submission/receipt evidence and outstanding findings.
- Inspection/maintenance evidence, unresolved backlog, responsible owners and correction dates.
- Mosquito-control referrals, ditch responsibilities and closure records.
November 5 review of DEP’s application tracker
DEP’s application tracker records receipt of FLR04E084-005-MS2A on April 20, 2023 and lists agency action as pending in data current November 4, 2026. The event table also shows that DEP began waiting for additional information on April 20, 2023. The completion field is blank.
The recorded receipt date corroborates the April 2023 timing in the county’s June 2025 statement. The application file, any subsequent correspondence, written Cycle 4 guidance and present coverage determination remain open. Report filing dates and compliance require separate evidence.
Reviewed November 5, 2026, 4:43 p.m. Central. To reproduce the lookup, enter FLR04E084-005-MS2A in Application Number. Florida DEP permit application search.
November 4 review: DEP records index located
Reviewed November 4, 2026, 7:54 a.m. Central. Tommy Moore’s November 3 response (5:06 p.m. Central), case 00251779, supplied a facility records link for FLR04E084. No individual records were attached to the reviewed message. DEP described this as its responsive-records response; that agency statement does not independently establish completeness.
Independently observed: DEP’s original electronic-records index identifies WALTON COUNTY, program NPDES_SW, and displays 56 entries across two pages (50 and 6). Both pages were inspected. Selected relevant entries are listed below, with DEP catalog 29 identifiers so copies can be requested precisely.
| Index document date | DEP subject | Catalog GUID |
|---|---|---|
| 2026-10-06 | COMPLAINT - 129 BUDS LN | 29.612447.1 |
| 2026-04-13 | YEAR 8 ANNUAL REPORT | 29.600720.1 |
| 2026-04-13 | WALTONCO_084_C5Y2_AR | 29.597807.1 |
| 2025-12-05 | ID_PITS BAYSHORE DR_RESOLVED | 29.585414.1 |
| 2023-06-19 | WALTON_C4Y4_AR_REVIEW & CLOSURE | 29.506421.1 |
| 2023-05-23 | NOI | 29.531337.1 |
| 2022-11-04 | YEAR3_AUDIT REPORT | 29.510347.1 |
| 2022-08-12 | YEAR3_AUDIT NOTIFICATION | 29.510346.1 |
| 2021-04-12 | WALTON COUNTY_CYCLE 4_YEAR 2_ANNUAL_REPORT_PACKAGE | 29.461036.1 |
| 2020-09-11 | WALTON COUNTY ILLICIT DISCHARGE CONCERN - RESOLVED | 29.461037.1 |
| 2018-10-15 | WALTON_COUNTY_CYCLE_4_NOTICE_OF_RENEWED_PERMIT_COVERAGE | 29.461032.1 |
| 2017-12-04 | WALTON_COUNTY_CYCLE_4_PERMIT_RENEWAL_PACKAGE | 29.461035.1 |
Access limitation: Initial text retrieval returned an incomplete document table. Browser access displayed the full index, but the tested April 2026 annual-report View link did not yield a readable file or captured download; direct export and pagination retrieval returned HTTP 403. This is verified access to an index, not completed production and review of the underlying documents. DEP’s portal also cautions that its data may be incomplete. The 56 entries are not necessarily 56 unique documents.
What the dates establish: These are the portal’s “Document Date” values, not independently verified submission, receipt, approval or deadline dates. The two April 13, 2026 report entries use identifiers ending 004 and 005; their relationship, reporting periods and receipt evidence remain unverified. The May 23, 2023 NOI index date does not establish or disprove the county’s attributed April 2023 submission date. A title containing “closure” or “resolved” is index metadata, not an independently reviewed finding.
Still unknown: Current coverage dates; renewal completeness and disposition; DEP’s instruction concerning continued Cycle 4 implementation; applicable report periods and due dates; actual receipt timestamps; audit findings, corrective actions and closure evidence; and whether responsive correspondence is absent from this unrestricted index. No current compliance determination or violation is established by this review. Unavailable records and absence from an index are not proof of nonfiling or a violation.
Follow-up sent November 4: Doug Liles replied to Tommy Moore in the existing case requesting accessible copies/direct downloads, prioritized by the catalog identifiers above, plus the remaining original-scope records, receipt evidence and clarification of index completeness. No fees or chargeable work authorized. Underlying-document review remains open.
6 · Original documents and sources
DEP original facility index: FLR04E084 · County request 26-915 · Protect30A evidence register. Agency portals may require interactive access. The detailed index review above supplies precise catalog identifiers for requesting copies.
- Walton County NPDES Stormwater Management Program — links to the county’s posted MS4 reports.
- County 2023–2024 Phase II MS4 report — reporting period and named responsibilities.
- Florida DEP Phase II MS4 requirements — reporting schedule.
Protect30A publishes independent public education and advocacy. Original records control. Explore the stormwater hub · Source library
7 · Updates, corrections and contact
- November 5, 2026, 4:43 PM Central — Added DEP’s application receipt date, pending action and open additional-information event. Preserved the distinction between application tracking and a coverage determination. The designated mailbox search found no new agency reply.
- November 4, 2026, 4:24 PM Central: Added routes between the records hub, source library, evidence findings and structured register. Distinguished page edits from source-review cutoffs. This editorial update adds no new agency correspondence, record examination or compliance finding.
- November 4, 2026, 4:17 PM Central: Weekday monitoring activated. Rechecked the designated mailbox: no new reply located. County NextRequest page requires sign-in to inspect details; DEP’s first index page remains visible, but the tested annual-report View link yielded no readable document. Removed private mailbox references from the public register; public source summaries remain linked. No new compliance finding.
- November 4, 2026, 3:35 PM Central: Added DEP’s November 4 processing reply, refreshed the mailbox-search cutoff and examined maintenance totals in the county’s posted report. Technical search-access checks passed; actual search indexing and AI citation remain unverified.
- November 2: Original meeting brief and coordinated requests; agency acknowledgments preserved.
- November 4, 7:54 a.m. Central: Register updated with DEP’s November 3 response, index review, access limits and accessible-copy follow-up.
- November 4, 2026, 3:28 PM Central: Page reorganized around a direct answer, evidence table and dated open questions. County status now explicitly states its November 2 correspondence cutoff. No new underlying-document review or compliance finding is implied.
Method: Protect30A separates examined source content, index metadata, attributed statements and unanswered questions. Original agency records control. Later evidence may change the answer; substantive corrections will be recorded here. No independent technical reviewer is identified for this edition.
Submit evidence or request a correction. Include the claim, source document, date and relevant page. Avoid sending private personal information.
Original November 2 meeting brief (PDF) — historical v1.0; does not incorporate subsequent updates.
Historical context and original meeting questions
Newly located historical correspondence
In a June 3, 2025 email to Darrin Dunwald, Environmental Manager Melinda Gates stated that Walton County had submitted its MS4 renewal in April 2023 and that DEP had instructed it to continue implementing Cycle 4 while review was pending. She also stated that the county was implementing measures in the renewal application.
Evidence limit: This is an attributed county statement located in correspondence forwarded June 5, 2025. It is not independent proof of DEP’s instruction, the application’s completeness, or current coverage/compliance. Both agencies have now been asked for the underlying records and subsequent disposition. An expiration date alone should not be treated as proof of a coverage lapse.
Verified public records: The county posts 2022–2023 and 2023–2024 MS4 reports. The latter covers October 15, 2023–October 14, 2024. Public posting does not prove DEP receipt. DEP generally requires annual reports in the first five-year cycle, then reports in years two and four unless it requires more frequent reporting. Sources 1–3.
Not yet verified: Current coverage and renewal status, applicable filing deadlines, DEP receipt of required filings, and outstanding deficiencies. The June 2025 county statement is summarized above; the underlying DEP instruction and current disposition remain unverified. This brief does not establish a permit violation.
1 · Define exactly what is overdue
“When staff said we were not up to date, precisely what was overdue?”
Request: Each missed permit condition, filing, inspection, maintenance task or corrective action; its original deadline; the date staff identified it; and its current status. Distinguish paperwork gaps from unfinished field work.
2 · Prove coverage and required submissions
“Show us current permit coverage and what DEP actually received.”
Request: Permit number and coverage dates; DEP acknowledgment; renewal Notice of Intent; current Stormwater Management Program; and required reports for the current and preceding permit cycles, with due dates, submission receipts and DEP deficiency correspondence. Explain years when no report was required.
3 · Show the work and the correction plan
“What records support the reported work, and what remains unresolved?”
Request: Asset and outfall maps; pond and inspection logs; illicit-discharge and construction-enforcement records; maintenance work orders; and an unresolved-problem list showing location, ownership, responsible department, interim action, cost and target completion date. Include a shared mosquito-control referral and closure log; distinguish mosquito findings from permit violations.
The requested outcome
“Please deliver a written status table within 10 business days: obligation, due date, evidence, gap, owner and correction date. Who owns delivery?”
This is a proposed management deadline, not a statutory public-records deadline. Request an estimate before chargeable records work.
Responsibility check: The 2023–2024 report names Melinda Gates as program contact and Buddy Wright as responsible authority at that time. Confirm today’s assignments, including Scott Caraway’s role; do not infer current duties from the older report. Source 2.
MS4 records outcome brief · November 6, 2026
The records resolve when DEP logged the renewal application and identify county reporting that can be examined. Current coverage, filing timeliness and field completion still require separate records.
- Did DEP log the renewal application? Yes. DEP’s tracker lists application FLR04E084-005-MS2A as received April 20, 2023. Its November 4 data lists agency action as pending. The current authorization and any written continuation instruction remain open. Application tracker review and agency source.
- What reporting can residents inspect? Walton County publishes its 2022–2023 and 2023–2024 annual reports. The DEP index lists two report entries with an April 13, 2026 document date. The underlying files, applicable deadlines and DEP receipt records are needed to determine filing timeliness. DEP index entries and catalog identifiers · 2022–2023 county report · 2023–2024 county report.
- What maintenance did the county report? The 2023–2024 report records 116 ponds maintained and approximately 1,048 miles of roadway with ditch and swale maintenance. The report resolves the published program totals. Site-level completion, dates and backlog require work logs. County report, PDF page 13, BMP 6a 06.
Records requests 26-915 and 00251779 provide the follow-up trail. Request register.